There’s nothing like a critical deadline to spark creative engineering solutions. Trident was given only 3 days to install and startup a new DCS for Elkhorn Valley Ethanol plant. The project had more than 1,500 I/O connections that would require hours of painstaking installation and testing. Trident’s teams estimated it could take about a week to wire the system—and they only had a little over two days. That’s when inspiration hit Trident founder Jerry Wenzel. “There were literally thousands of […]